CO129-412 - Governor Sir May - 1914 [7-8] — Page 299

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All

!

290

"C".

List of a few letters sent to the Contractor.

5th February 1905.

19th June 1906.

Delay re delivery of granite,

Delay: asked contractor to give the work his personal attention.

17th November 1906. quarries were about to be let on lease,

asked the contractor to call re this matter,

19th October 1907.

Granite required, asked contractor to arrange without delay.

20th November 1908. Delay. Hasons required.

H

M

Bamboo men required.

23rd

4th January 1909.

29th

Concretors and Bricklayers required

Timber required. Floor boards must be cut

at the earliest date and panelling to Counts put into frame.

19th February 1909. General delay

7th July 1909.

28th 帅

29th December 1909.

a0-

do.

Timber.

5th

18th

11

3rd June 1910. 8th 14 4th July 1910

#1

13th January 1910.

22nd

17

3rd March 1910.

#

H

9 th 18th April 1910.

2nd May 1910

M

General delay

do.

Plasterers required.

do. and general delay

Timber

Asphalte: (not yet finished)

Asked contractor to take means to prevent theft of materials

Tiling and general delay,fittings to courts

Tiling. Timber

Fittings to courts,

Fitters required to dome

6th #

Delay re punching down.

14th #

"

Theft and breakage of tiles.

23rd August" 26th 6th October 1910

Π

16th November "

2nd February 1911.

Delay re concrete to inner dome

Delay re asphalting

Plasterers required.

Cement required. Plasterers and joiners required.

Electric Co. unable to proceed owing to want of labourers to cut holes.

Theft of tiles still in progress.